Electricity Regulation Act, 2006 (Act No. 4 of 2006)RulesGrid Capacity Allocation Rules3. Objectives of the Grid Capacity Allocation Rules |
| 3.1 | The objectives of these Rules are to: |
| (a) | promote investment in the Electricity Supply Industry (ESI); |
| (b) | ensure the efficient, fair, and reliable use of the electricity grid infrastructure; |
| (c) | improve capacity allocation to prioritise projects that are ready to connect while maintaining options for Applicants; |
| (d) | bring clarity and order to how grid capacity is allocated to potential generation and load projects; and |
| (e) | ensure that potential entrants to the industry have sufficient preliminary information to enable proper assessment and informed investment decisions. |