Electricity Regulation Act, 2006 (Act No. 4 of 2006)

Rules

Grid Capacity Allocation Rules

9. Revocations

Purchase cart Previous page Return to chapter overview Next page

 

9.1 The following aspects shall be the triggers for capacity revocation:
(a) Non-compliance with project milestones within the allocated timeframe.
(b) Termination of the connection agreement(s) and/or related contracts.

 

9.2 However, the NSP shall not revoke capacity for a project if the delays are caused by a force majeure event.