Electricity Regulation Act, 2006 (Act No. 4 of 2006)RulesGrid Capacity Allocation Rules9. Revocations |
| 9.1 | The following aspects shall be the triggers for capacity revocation: |
| (a) | Non-compliance with project milestones within the allocated timeframe. |
| (b) | Termination of the connection agreement(s) and/or related contracts. |
| 9.2 | However, the NSP shall not revoke capacity for a project if the delays are caused by a force majeure event. |