Occupational Health and Safety Act, 1993 (Act No. 85 of 1993)RegulationsConstruction Regulations, 20144. Notification of construction work |
| (1) | A contractor who intends to carry out any construction work other than work contemplated in regulation 3(1), must at least 7 days before that work is to be carried out notify the provincial director in writing in a form similar to Annexure 2 if the intended construction work will— |
| (a) | include excavation work; |
| (b) | include working at a height where there is risk of falling; |
| (c) | include the demolition of a structure; or |
| (d) | include the use of explosives to perform construction work. |
| (2) | A contractor who intends to carry out construction work that involves construction of a single storey dwelling for a client who is going to reside in such dwelling upon completion, must at least 7 days before that work is to be carried out notify the provincial director in writing in a form similar to Annexure 2. |